Time Step Simulation: Schedule Subscriptions Page

Concept Link IconSee Also

 

This sub-page is found on the Input page of the Time Step Simulation dialog and is used to display all of the schedule subscriptions and their properties. Once a schedule has been created, we can assign an object field, such as the status of a transmission line or the MW output of a generator to the schedule by means of a Schedule Subscription. The object field will follow the schedule "shape" in time. The use of Schedule and Schedule Subscription objects gives us great flexibility in specifying how quantities should vary.

The most relevant options of the local menu, obtained by right-clicking on the grid of this page are:

Schedule Subscriptions Page Local Menu Actions

Insert New Subscription

Use this option to define a new schedule subscription through the Schedule Subscription Dialog.

Delete

This option deletes the current schedule subscription.

Show Dialog

This option brings up the Schedule Subscription Dialog with the information of the current schedule subscription.

 

Schedule Subscriptions Page Fields

The Schedule Subscriptions Page shows the following information:

Object

Object Type: Generator, Load, Line/Transformer, Shunt, Area, Transaction, Zone, Interface, or DC Line

Object IDs

Are explained in the following table:

 

Object Type

Object ID1

(Numeric)

Object ID2

Numeric

Object ID3

String[2]

Generator

Bus Number

 

Gen ID

Load

Bus Number

 

Load ID

Line/Transformer

From Bus Number

To Bus Number

Circuit ID

Shunt

Bus Number

 

Shunt ID

Area

Area Number

 

 

Transaction

From Area Number

To Area Number

ID

Zone

Zone Number

   

Interface

Interface Number

   

DC Line

Rectifier Number

Inverter Number

ID

 

Object Field

Field that subscribes to the schedule.

Schedule Name

Name portion of the schedule name and suffix identifier.

Schedule Suffix

Suffix portion of the schedule name and suffix identifier.

Active

Set this to YES so that the schedule values will actually be applied to the power system.

Relative

If this is NO the field takes the exact schedule values. If this is YES the schedule takes the value of the schedule scaled by a multiplier plus Value Shift.

Multiplier

Scaling factor used when the subscription is Relative.

Value Shift

Shift value used when the subscription is Relative.

Delay/Advance?

Indicates if the schedule should be delayed or advanced to a new point indicated by the shift values. A delay will cause the schedule to start later in time. An advance will cause the schedule to start earlier in time. See the Schedule Subscription Dialog for more details on this option.

Day Shift

Number of days of the schedule time delay/advance. 

Hour Shift

Number of hours of the schedule time delay/advance.

Minute Shift

Number of minutes of the schedule time delay/advance.

Second Shift

Number of seconds of the schedule time delay/advance.

 

Schedule Subscriptions can be saved and loaded from auxiliary files using options found on the local menu obtained by right-clicking on the table or using the case information toolbar.